Bay Lane Reconstruction

Backgound Information


The City of Muskego has budgeted for the survey and preliminary design for the potential reconstruction of Bay Lane, from Woods Road to Janesville Road (CTH “L”). Design alternatives have been examined for the reconstruction of Bay Lane and include the three option shown below. Design is budgeted in 2018, with construction in 2019.   

Should you have any questions please contact Mike Paulos, City Engineer, at (414) 266-9086 or via e-mail Mike.Paulos@graef-usa.com or Daniel Flamini at 262-679-4156 or via e-mail Dflamini@cityofmuskego.org 

Public Informational Meeting


The first Public Information Meeting was held July 15, 2015 and included presenting the alternatives below.  The project is budgeted for 2018 design and 2019 construction.  Future public information meetings will be published here.

Design Information


Preliminary Alternatives



Three reconstruction alternatives are being evaluated by the City of Muskego and include the options listed below and the associated .pdfs below.  Please take the time to look at the options and provide input by emailing David Simpson at dsimpson@cityofmuskego.org.  

1.         Full reconstruction of the roadway as an urban section with concrete curb and gutter, storm sewer, concrete driveway approaches, six foot wide pathway on the east side of the roadway and installation of an asphalt pavement for the road. The width of the roadway would be 28 feet from the face of curb to face of curb.  Temporary grading easements may be needed from some property owners.

2.         Full reconstruction of the roadway with rural type ditches and the construction of a six foot wide pathway along the east side of the roadway on the backside of the ditches. The pavement width would be 26 feet wide with 3 foot stone shoulders on both sides.  This alternative would require property acquisition in many areas to allow for the installation of ditches and the pathway. This option was not fully designed because during the initial design it was determined that a large amount of right-of-way would be needed.  

3.         Reconstruction of the roadway using a hybrid approach by placing curb and gutter where required to stay within the existing right of way and using a rural section where it works best for storm water conveyance or where curb and gutter cannot be used because of grading challenges. The widths of roadway section would follow those noted above. This alternative would include a six foot wide pathway on the east side of the roadway.  By utilizing this alternative we would be able to keep the vast majority of improvements within the existing right of way with only temporary grading easements being needed from some property owners. 

Alternate 1
Alternate 2
Alternate 3